HS2 £800m over cost target

This post has already been read 1118 times!

The HS2 project is reporting huge cost pressures from overrunning enabling works and higher building cost estimates for the London terminus at Euston.

The £40.3bn first phase of the enabling works were revealed in the first report to Government by HS2 Minister Andrew Stephenson today.

The latest projections are still in their early stages, the forecast is still within the Government’s extended funding of £44.6bn.

Although the HS2 project has still to factor in the cost impact of Coronavirus, which will be detailed within the next six months.

£9.6bn has already been spent already, a further £11.5bn is contracted, and £13.9bn is yet to be contracted and remains an estimate.

The overall target cost also includes £5.3bn contingency in funding for managing the risk and uncertainty that are an inherent part of delivering these type major projects.

Of the £800m cost pressure identified so far, around £400m is attributed to enabling works overruns.

The project started in 2017 but the enabling works have encountered more significant challenges than anticipated, such as the need to safely remove more asbestos than expected which in turn has escalated costs.

More detailed scoping of Euston Station redevelopment has identified a significant cost pressure, currently reported at £400m.

Stephenson warned that further work is ongoing to validate these initial estimates and this could identify further pressure.

Andrew Stephenson commented saying that “As this remains at the design stage, work is underway to consider opportunities, efficiencies and scope reductions in order to redress these pressures and we will report further on this in the next report,” report he added.

On Phase One, the Delivery into Service date range for initial services from Old Oak Common to Birmingham Curzon Street remains 2029 to 2033.

“HS2 continues to predict that it will provide services within this range but notes some pressures on the earliest date from COVID impacts and delayed handovers from enabling works, which it is seeking to mitigate.

“Schedule estimates will be more reliable once the main works are fully mobilised next summer and once the Rail Systems elements have been contracted.”

Initial opening of services from Euston remains 2031-2036, subject to further work on the study of design and delivery options.