Brick work contractors grind to halt as cement shortages strike
This post has already been read 3048 times!
Cement supplies are becoming increasing scarce with not only bagged products but silo refills have been put on allocation by major cement suppliers limiting their ability to manufacture and supply leaving large sites waiting up to four weeks for refills.
Remix have temporarily stopped taking orders this week although it hopes to get back on track next week with Euromix also writing to customers warning of disruption to supplies.
Eve Livett, Chief Executive Officer of the Association of Brickwork Contractors, commented saying that: “The majority of our 30 member contractors are experiencing problems with supply.
“If this continues it is going to scupper progress of works.”
“It is vital that the wider industry be made aware of this so that a collaborative approach can be made with main contractors and their brickwork subcontractors.”
Larry Dale, CPI Euromix’s managing director, commented saying that: “With immediate effect, our principle cement supplier has placed CPI and other customers on allocation, this will limit our ability to manufacture and supply mortar in certain locations.
“We will endeavour to provide the best service that we can, however these new production constraints will inevitably cause disruption in our ability to supply.
“We will provide the best information we can at the time of ordering in terms of indicative order call off times, we very much hope that this is a short term issue but in any event is out of our control at this time.”
Mineral Products Association chief executive Nigel Jackson, speaking on behalf of cement suppliers, said that a mix of high demand, kiln shutdowns for maintenance and trouble finding hauliers was causing localised delays.
“Where demand exceeds supply capacity longer lead times may be expected.
“As production catches up it shouldn’t be long before supplies are back to normal depending on how long this surge in pent-up demand actually lasts and subject to transport availability.”